Regulatory Change – IDEM Transitioning from Rule 6 to Industrial Stormwater General Permit (ISGP)
IDEM issued the final Industrial Stormwater General Permit (ISGP) on December 30, 2025. This permit will replace the permit-by-rule codified in 327 IAC 15-6 (“Rule 6”) which has been the stormwater permit in Indiana for the last 20+ years. IDEM has not yet provided the Notice of Intent (NOI) form/mechanism to transition permit coverage from Rule 6 to the ISGP. Once they have made this available, facilities have 180 days to submit their NOI. Concurrently, IDEM is in the process of completing the rulemaking which will repeal Rule 6. The ISGP contains a number of new/updated requirements that will need to be implemented by all facilities that are currently covered under Rule 6. August Mack has developed a scope of work that includes the following to assist facilities in transitioning to the ISGP. Steps 1 and 2 can and should be started ASAP, along with any on-site training, so the facility can be set up for full compliance with the ISGP once coverage is transitioned.
Permit Transition
SWPPP Update
- SWPPPs must be updated to align with ISGP requirements before an NOI can be submitted.
Receiving Water Harness Sampling (or coordination)
- For sites that are subject to hardness-dependent benchmark monitoring parameters, the permit requires permittee to take a sample of the receiving water to obtain the hardness value.
- This value must be obtained before an NOI can be submitted.
- August Mack can perform the sampling or provide off-site support/coordination (laboratory coordination, bottle order, etc.).
Notice of Intent (NOI) Preparation
- Due 180 days after IDEM makes the form/mechanics available.
- Will be submitted on IDEM’s Regulatory Service Portal (RSP).
Permit Compliance/Implementation
Benchmark Monitoring (or coordination)
- Facilities are required to sample for sector-specific parameters identified in Appendix A of the permit. Sector is determined by SIC code. The ISGP requires that four samples be collected during the first two years (eight calendar quarters) of permit coverage.
- August Mack can perform the sampling or provide training and off-site support/coordination (laboratory coordination, bottle order, etc.).
- It should be noted that IDEM’s draft version of the ISGP required benchmark monitoring for COD, TSS and pH for ALL facilities. This universal benchmark monitoring requirement was removed in the final version, so sites are only required to conduct benchmark monitoring for the pollutants listed in their industrial sector.
Quarterly Visual Assessments (QVAs)
- All permittees will be required to complete QVAs during rain events.
- August Mack can perform the QVAs or provide training so an onsite facility representative can perform the QVAs.
Discharge Monitoring Reports (DMRs)
- All discharge monitoring reports (DMRs) must be completed through the web-based netDMR reporting portal.
- August Mack can help with netDMR setup and DMR preparation.
Annual Report
- The Annual Report is not required to be submitted under the ISGP. It only needs be retained onsite and provided to IDEM upon request.
- Must include a re-evaluation of receiving water body to check for impairments.