Stormwater Permitting in Indiana: 7 Key Changes You Need to Know

Published On: April 16, 2025

The Indiana Department of Environmental Management (IDEM) is in the process of transitioning their stormwater permits from a permit by Rule (previously referred to as “Rule 6”) to a Master General Permit. Rule 6 was codified into the Indiana Administrative Code (IAC) in 2003 and has remained unchanged since. Rule 6 does not align with what other states and Federal guidelines require, thus the implementation of a new permit, the Indiana Industrial Stormwater General Permit (ISGP). ISGP was previously out for public notice and received comments from the regulated community that IDEM will have to address and respond to before the ISGP will be issued. The current date of the ISGP being implemented is unknown at this time, but IDEM is hopeful for early 2025. Until it is issued, facilities should continue to comply with Rule 6’s requirements. After transitioning to the ISGP, IDEM will review and re-issue the ISGP every five years as required by federal regulations. Below are seven key changes you need to know about the ISGP.

1. Transitional Coverage

To obtain transitional coverage for existing permit holders, a new Notice of Intent (NOI) must be submitted to comply with the requirements of the ISGP within 180 days following the date that IDEM makes the NOI available to the permittee.

 

2. Stormwater Sampling Requirements

Under the draft ISGP, all facilities will be required to conduct benchmark monitoring for Total Suspended Solids (TSS), Chemical Oxygen Demand (COD), pH and any additional pollutants identified in the permit appendices for its particular industrial sector.   Four samples will need to be collected during the first two years (eight calendar quarters) of permit coverage.  Each of the four different calendar quarters must be represented by a benchmark sampling event.

 

If the average of the four collected samples is below USEPA’s “benchmark” concentration for all pollutants, the benchmark monitoring condition is satisfied for the remainder of the five-year permit term.  If the average concentration exceeds the benchmark for any outfall/pollutant, corrective action must be taken and another set of four samples (over the subsequent two years) must be collected.

 

If less than four benchmark samples have been taken, but the results are such that an exceedance of the four quarter average is mathematically certain (i.e., if the sum of quarterly sample results is more than four times the benchmark level) this is considered a benchmark exceedance.  IDEM will continue to allow for designation of outfalls as “substantially similar” which can allow for monitoring one outfall to represent multiple outfalls if the drainage areas are substantially similar.

 

3. Impaired Water Body Segment Identification

In addition to benchmark monitoring, the ISGP requires that permittees identify if they discharge to an impaired water body segment.

 

If it is determined that the water body segment is impaired, permittees are required to conduct annual monitoring for pollutants for which the water body is impaired and are associated with the industrial site activity.

 

If the pollutant of concern is not detected and not expected to be present in the facility’s discharge, the permittee may request to discontinue impaired waters monitoring for that pollutant.

 

4. Quarterly Stormwater Site Inspections

The ISGP will require quarterly storm water site inspections that are intended to address housekeeping, best management practices (BMPs) and detect any issues that could affect storm water discharge.

 

5. Quarterly Visual Assessments

The ISGP requires quarterly visual assessment (QVAs) of storm water discharge.  During these QVAs, a storm water sample is collected in a clean, clear jar and visually inspected for abnormal attributes (e.g., color, sheen, turbidity).  The draft ISGP does not address whether these QVAs may be waived or be conducted simultaneously in instances where benchmark monitoring is also being conducted during the first two years of permit coverage.

 

6. Storm Water Pollution Prevention Plan (SWPPP)

SWPPPs will need to be updated to reflect the new permit monitoring requirements.  The SWPPPs are not required to be submitted to the IDEM.

 

7. Reporting

All facilities will be required to prepare Discharge Monitoring Reports (DMRs) and Annual Reports (ARs). Under the draft ISGP, all DMR reporting must be completed through the web-based netDMR reporting portal. DMRs will be due by the 28th day following each monitoring period.  Presumably, each calendar quarter for the first two years of permit coverage will be identified as a monitoring period.  IDEM will pre-populate DMR frequency and parameters for each facility.  Due to the volume of facilities that will obtain sample coverage, this may take IDEM some time.  In the interim, IDEM will continue to allow paper submittals.

 

The Annual Report is required to be prepared no later than 365 days from the effective permit coverage start date and each successive 365 days from that date in years two through five.  The Annual Report is not required to be submitted under the ISGP.  It only needs be retained onsite and provided to IDEM upon request.